Infrastructure : Completed Projects

Concrete work at P No 26 B MIT College Kothrud Area Road

Concrete work at P No 26 B MIT College Kothrud Area Road
Authorized by Pune Municipal Corporation
Stipulated date of Completion : 23/12/2013
Actual date of of Completion : 10/05/2014

Development work at P No 34 A Road (Ajanata Society Kothrud ) .

Development work at P No 34 A Road Ajanata Society Kothrud.
Authorized by Pune Municipal Corporation
Stipulated date of Completion : 12/12/2013
Actual date of of Completion : 31/05/2014

Development of Concrete Road In Prabhag No.9 Hotel Sarja to Panjab National

Development of Concrete Road In Prabhag No.9 Hotel Sarja to Panjab National
Authorized by Pune Municipal Corporation
Stipulated date of Completion : 12/02/2013
Actual date of of Completion : Work in Progress

Construction of RCC Box Culvert & Removing Old Pipe culvert at Bhoiraj Society

Construction of RCC Box Culvert & Removing Old Pipe culvert at Bhoiraj Society
Authorized by Pune Municipal Corporation
Stipulated date of Completion : 02/02/2013
Actual date of of Completion : 25/07/2013

Baner Pimpale Nilakh Approch Road

Devlopment of approch Rd at Baner Pimplenilakh Bridge in S.No. 159 to 134. Authorized by Pune Municipal Corporation
Stipulated date of Completion : 17/02/2011
Actual date of of Completion : 30/1/2011

Construction Box Culvert at Harekrishna Mandir Path

Devlopment of Construction Box Culvert at Harekrishna Mandir Path. Authorized by Pune Municipal Corporation
Stipulated date of Completion : 31/06/2011
Actual date of of Completion : 15/06/2011

Construction of Box Culvert at Ivory Estate, Baner

Construction of Box Culvert at Ivory Estate, Baner. Authorized by Pune Municipal Corporation
Stipulated date of Completion : 5/7/2011
Actual date of of Completion : 24/4/2011

Development of Dahanukar Main Rd & concrete work

Development of Dahanukar Main Rd & concrete work. Authorized by Pune Municipal Corporation
Stipulated date of Completion : 29/04/2012
Actual date of of Completion : 12/04/2012

Main Road at Kondhva , Lullanagar Chowk to Bhariav Mandir C.C.Road.

Development of Main Road at Kondhava , Lullanagar Chowk to Bhariav Mandir C.C.Road.From Kondhva Gaonthan. Authorized by Pune Municipal Corporation
Stipulated date of Completion : 25/10/2011
Actual date of of Completion : 8/10/2011

Construction of Box Culvert on Nala at Sahajanand Society

Construction of Box Culvert on Nala at Sahajanand Society . Authorized by Pune Municipal Corporation
Stipulated date of Completion : 31/06/2011
Actual date of of Completion : 18/06/2011

Thin White Topping Pavement & allied works, Dahanukar Colony

Construction of Thin White Topping ( TWT ) Pavement and allied works for roads in ward No 108 ( Dahanukar Colony Lane No 1,15to 17 ). Authorized by Pune Municipal Corporationi
Stipulated date of Completion : 3/9/2009
Actual date of of Completion : 5/3/2009

Development Trimix Concrete work, Ghorapade Peth

Development Trimix Concrete work at w.no. 83 horapade Peth 669 to 692 Ghorapade Peth Jahangirdar Maruti Mandir area.. Authorized by Pune Municipal Corporationi
Stipulated date of Completion : 14/09/2011
Actual date of of Completion : 2/09/2011

Joging track at sambhji Bridge to omkareshwar river side

Development of joging track at sambhji Bridge to omkareshwar river side w. no. 52. Authorized by Pune Municipal Corporationi
Stipulated date of Completion : 7/7/2011
Actual date of of Completion : 31/7/2011

channal Work at Rajaram Bridge to Warje Bridge Express Highway

channal Work at Rajaram Bridge to Warje Bridge Express Highway Ch.0 to1250. Authorized by Pune Municipal Corporationi
Stipulated date of Completion : 23/01/2008
Actual date of of Completion : 13/01/2008

Right side channal from Mathre Bridge to Rajaram Bridge

Remaining work of left side channal from Ravindra Mhatre Bridge to Rajaram Bridge under JNNURM. Authorized by Pune Municipal Corporationi
Stipulated date of Completion : 12/7/2010 (Exculding Monsoon)
Actual date of of Completion : 2/12/2010

Gabbion Retaining wall work at Sangam Bridge

Development of Gabbion Retaining wall work at Sangam Bridge. Authorized by Pune Municipal Corporationi
Stipulated date of Completion : 12/9/2010 (Exculding Monsoon)
Actual date of of Completion : 28/11/2010

Construction of Box culvert infront of IISER Pashan

Construction of Box culvert infront of IISER Pashan. Authorized by Pune Municipal Corporationi
Stipulated date of Completion : 30/02/2012
Actual date of of Completion : 2/02/2012

Other Completed Works

  • Supply Metal & Sand at Yerwada Mix Plant for P.M.C.
  • Cycale Track at Bibewadi Road ( Part - 1 )
  • Cycale Track at Bibewadi Road ( Part - 2 )
  • Retaining wall at Matoshree Vrudhashram
  • Development Road & Bridge on Canal at Sinhagad Rd To Janata Vashat
  • Construction of Thin White Topping ( TWT ) Pavement and allied works for roads in ward No 126 ( M.Gandi to Sahakarnagar No 2 )
  • Making Concrete work at Hadapsar Gadital Hanuman Mandir to Tuljabhavi Vasahat
  • Devlopment aproch Rd & Construction Flyover at PMC to PCMC Joint ot Mula River Baner Pimplenilekh
  • Providing & Spreading RMC for Reparing of Rd in Working Area of DYCE
  • Construction of Culvert on 100 ft Dp Road at River side near Karve Rd Smashan Bhumi
  • Link Road at w.no. 117 Lahane Path to Shankar Shet Road.
  • Development of Approach Road at Sinhagad Road to Janata Vashat

Other Completed Works

  • Leveling Of Chambers at Tilakroad Vishrambagawada Ward Office
  • Development of Footpath,Side patti, fixing paving blocks on different Roads in City ( Tilak Rd.Vishrambag Wada) .
  • Construction Box Culvert At w no 110 Near Popular Nagar
  • Construction of Thin White Topping ( TWT )Pavement and allied works for roads in Ujawi Bhusari Colonym PMT Depo to Poud Road to New India School
  • Making of Concrete Road at w.no. 95 S.49 Lane No 9 Nhawale Nagar Murey
  • Construction of Thin White Topping ( TWT )Pavement and allied works for roads in
  • Development open Space at Wanwadi Abhuday Society.Ward no 126 Taljai Mandir Near Forest Rd
  • Development Garden at Kothrud Alkapuri Soc.
  • Development of joging track at Baba Bhide Bridge to omkareshwar Causeway.
  • Developing work For Beautification of Alankar Nala & Sanapati Bapat
  • Developing 18 mtr. D.P. Rd. at ward no. 28 Baner Balewadi sr.no Land 2 Pearl Society
  • Main Drainage Line work at S.No. 33,34 & D.P Road of Internal Balewadi Area.

Other Completed Works

  • Retaining wall at Fursungi Dafan Bhumi
  • Development C.C. Main road at kondhava Lullanagar to ashoka muse road & Development of Maruti gali, Pandurag Gali, Bhairnath Gali Road
  • Development Road w no 49 Old Market where Kasba Peth To Trimurti Mitra Mandal.
  • Retaining wall at ward no 83 P.M.T. Colony Laying of Dranige Line at ward no 83 Ghorpade Peth Udhyan to P.M.C. Karmshcool.
  • Concrete Road at Aundh, Ghole Rd & Pund Road
  • UTWT Rd at Wd. no. 115 Laxminagar Vasahat
  • Development Work in Ward no. 115
  • UTWT Rd at Wd. no. 115 Tulsibagwale Colony
  • UTWT Rd at Wd. no. 115 Mhada
  • Retaining Wall At Ward No.53 PMC Colony Pandava Nagar
  • Development Road w no 49 ,917 Kasba Peth
  • Remaining Work Of Wall at Ward no.130 CYDP School

Other Completed Works

  • Concreting Of Road At Shewalwadi Jakat Naka
  • Construction of Retaining wall at Thosar Paga Dafan Bhumi
  • Construction of Retaining wall at Thosar Paga Dafan Bhumi at Poona Hospital Side
  • Construction of Retaining wall at Thosar Paga Dafan Bhumi at River Side
  • Construction Of Retaining Wall at Ward no.130 CYDP School
  • Developing Of Road At Shewalwadi Jakat Naka
  • Developing Foothpath At Ward No.39 sarita Nagari